Task was the development of a project baseline schedule for all works with project cash flow and uploads all resources for a project subcontractor. Acted as consultant for contract administration and claims.
Claims included cost claims, penalties or charges reduced, and delay damages avoided via EOTs.
Claims preparation and negotiations with client resulted in extensions of time of 6 months.
75 M EGP || 5 M USD
Tower Developments
Egyptian Consulting Group (ECG).
Mountain Construction.
External and internal finishing works, sanitary works, internal electrical works and mechanical works for 12 buildings, and swimming pools in the general area.
Port Saied, Egypt