Task included preparing arbitration documentation and assisting in the arbitration procedures for nearly 50% of original cost.
Won arbitration for 19.25 M EGP (2.75 M USD) from the Egyptian General Authority for Coastal Protection in 2014 as a claims & arbitration consultant for the Arab Contractors, Alexandria Branch. The amount included altered prices for unforeseeable adverse conditions, quantity variations, and prolongation costs.
150 M Egp || 25 M USD
Egyptian General Authority for Coastal Protection
Arab Contractors
Construction of 9 seawater groins to protect the Western Coast
of Rosetta city in Egypt. The cost overruns reached 70%.
Rosetta, Egypt